Microsoft Project 2010 : Setting Up Cost Resources & Documenting Resources

2/7/2012 4:33:43 PM

Setting Up Cost Resources

Another type of resource that you can use in Project is the cost resource. You can use a cost resource to represent a financial cost associated with a task in a project. While work resources (people and equipment) can have associated costs (hourly rates and fixed costs per assignment), the sole purpose of a cost resource is to associate a particular type of cost with one or more tasks. Common types of cost resources might include categories of expenses you’d want to track on a project for accounting or financial reporting purposes, such as travel, entertainment, or training.

Cost resources do no work and have no effect on the scheduling of a task. The Max. Units Standard and Overtime pay rates and Cost/Use fields do not apply to cost resources. After you assign a cost resource to a task and specify the cost amount per task, you can then see the cumulative costs for that type of cost resource, such as total travel costs in a project.

The way in which cost resources generate cost values differs from that of work resources. When you assign a work resource to a task, the work resource can generate a cost based on a pay rate (such at $40 per hour for the length of the assignment), a flat per-use cost (such as $100 per assignment), or both. You set up such pay rates and cost per use amounts once for the work resource. However, you enter the cost value of a cost resource only when you assign it to a task. You can do so in the Cost field of the Assign Resources dialog box or in the Cost field of the Task Form with the Cost detail shown.

In this exercise, you’ll set up a cost resource.

  1. In the Resource Sheet, click the next empty cell in the Resource Name column.

  2. Type Travel and press the Tab key.

  3. In the Type field, click Cost.

    Setting Up Cost Resources

Documenting Resources

If a resource has flexible skills that can help the project, it is a good idea to record this in a note. In that way, the note resides in the project plan and can be easily viewed or printed.

In this exercise, you enter resource notes relevant to the new book launch project.You entered a task note via the Task Notes button on the Task tab of the Properties group. You can enter resource notes in a similar way (via the Notes button on the Resource tab of the Properties group) but in this exercise, you’ll use a different method. You’ll use the Resource form, which allows you to view and edit notes for multiple resources more quickly.

In this exercise, you’ll enter notes in the Resource Form.

  1. In the Resource Name column, click Toby Nixon.

  2. On the Resource tab, in the Properties group, click the Details button.

    Documenting Resources

    Tip

    You can also click Details, Resource Form on the View tab of the Split View group.

    The Resource Form appears below the Resource Sheet view.

    Tip

    In this type of split view, details about the selected item in the upper view (a resource, in this case) appear in the lower view. You can quickly change the selected resource name in the upper view by clicking directly on a name, using the up arrow or down arrow keys, or by clicking Previous or Next in the Resource Form.

    The Resource Form can display one of several details; initially it displays the Schedule details. Next you’ll switch it to display the Notes details.

  3. Click anywhere in the Resource Form.

  4. On the Format tab, in the Details group, click Notes.

    Tip

    Tip

    You can also right-click in the gray background area of the Resource Form and, in the shortcut menu that appears, click Notes.

    The Notes details appear in the Resource Form.

  5. In the Notes box, type Toby worked on launch campaigns for Toni Poe’s previous two books.

    Tip

    Notice that as soon as you started typing the note, the Previous and Next buttons changed to OK and Cancel.

  6. Click OK.

    In the Resource Sheet view, a note icon appears in the Indicators column.

  7. Point to the note icon that appears next to Toby’s name in the Resource Sheet.

    Tip

    The note appears in a ScreenTip. For notes that are too long to appear in a ScreenTip, you can double-click the note icon to display the full text of the note. You can also see more of long notes in the Resource Form or in the Resource Information dialog box.

    To conclude this exercise, you’ll add a note for one more resource.

  8. In the Resource Form, click Previous to shift the focus to Sharon Salavaria and display her details.

    Tip

    You can also click on Sharon’s name in the Resource Sheet view above the Resource Form.

  9. In the Notes box, type Sharon’s standard pay rate is adjusted for her half-time work schedule. Then click OK.

    Tip

    Finally, you’ll close the Resource Form.

  10. On the Resource tab, in the Properties group, click the Details button.

    The Resource Form is closed, leaving the Resource Sheet displayed.

    In this exercise, you’ve entered notes for some resources. This information is unique to those resources.

Clean Up

Close the Simple Resources file.

 
Others
 
- Microsoft Visio 2010 : Working Around the Diagram - Getting Started with a New Drawing
- Understanding the Microsoft Visio Object Model : Connectivity API
- Microsoft PowerPoint 2010 : Formatting Tables
- Microsoft PowerPoint 2010 : Inserting Tables
- Microsoft Excel 2010 : Printing in Excel - Printing in Portrait or Landscape Orientation & Centering a Worksheet on a Page
- Microsoft Excel 2010 : Printing in Excel - Working in Page Break Preview Mode & Printing a Worksheet on One Page
- Microsoft Access 2010 : Viewing a Sample Database & Creating a New Database
- Microsoft Access 2010 : Designing a Database
- Microsoft Outlook 2010 : Sending Text Messages from Outlook & Sending Mobile Alerts from Outlook
- Microsoft Outlook 2010 : Using Alerts and Mobile Features - Setting Up a Text Messaging Service
- Microsoft OneNote 2010 : Upgrading from a Previous Version
- Microsoft Word 2010 : Customizing Word - Changing Advanced Document Properties & Changing Research Options
- Microsoft Word 2010 : Customizing Word - Setting Advanced General Options & Setting Compatibility Options
- Microsoft Project 2010 : Setting Up Resources - Adjusting Working Time for Individual Resources
- Microsoft Project 2010 : Setting Up Resources - Entering Resource Pay Rates
- Microsoft Visio 2010 : Displaying the issues for the current selection
- Microsoft Visio 2010 : Displaying the rule for a selected issue
- Accessing PowerPoint on the Web and Mobile Devices (part 2) - Setting SkyDrive Permissions
- Accessing PowerPoint on the Web and Mobile Devices (part 1) - Setting Up SkyDrive
- Microsoft PowerPoint 2010 : Managing Themes
 
 
Most View
 
- Adobe Flash Professional CS5 : Manipulating Symbols in 3D Space (part 1) - Controlling the camera view: Perspective and vanishing point
- Adobe Flash Professional CS5 : Manipulating Symbols in 3D Space (part 2) - Transforming symbols with the 3D Rotation tool
- Mobile Web Apps : Loading Pages (part 3) - Going Backwards
- Microsoft Dynamics AX 2009 : Design and Implementation Patterns (part 1) - Class-Level Patterns
- Introducing the iPhone SDK (part 5) - Programming Paradigms
- Beginning Android 3 : Set Up the Emulator
- Microsoft Excel 2010 : Analyzing Worksheet Data - Adding Data Validation to a Worksheet
- Microsoft Dynamic CRM 2011 : Resolving a Service Request Case
- Accessing PowerPoint on the Web and Mobile Devices (part 1) - Setting Up SkyDrive
- Microsoft Excel 2010 : Using Print Preview